Investigators have determined the electrical facility fire which forced the closure of London Heathrow was triggered by a short-circuit from moisture entering high-voltage infrastructure – a problem detected seven years earlier but left unaddressed.
The fire on 20 March, and Heathrow’s shutdown the following day, resulted in 121 flights being diverted and some 1,300 more being cancelled.
Three transformers at the North Hyde electrical facility were used to feed one of three substations at Heathrow.
Elevated moisture readings in one of the transformers’ bushings – which insulate the high-voltage conductors from other structures – were detected during maintenance in July 2018.
The reading was significant enough to indicate an “imminent fault” and require replacement of the bushing, states National Energy System Operator’s inquiry into the 20 March fire.
While the reading was recorded by National Grid Electricity Transmission, which owns the high-voltage network, the inquiry says “mitigations appropriate to its severity were not actioned”.
“The controls in place were not effective and failed to identify subsequently that action had not been taken in relation to the elevated moisture reading,” it adds.
Multiple attempts were made to schedule maintenance on the transformer but, owing to priority considerations and the need to keep systems running, none of these went ahead.
“The issue therefore went unaddressed,” the inquiry states.
Presence of moisture caused a “catastrophic” short-circuit, it states, with electrical arcing igniting oil used as a coolant.
Protections automatically disconnected the other two Heathrow-feed transformers, meaning that the airport lost one of its three substations. The airport’s management opted to reconfigure distribution from the two remaining substations, but this took several hours to carry out.
“The power outage and closure of Heathrow airport were hugely disruptive and our report seeks to improve the way parties plan for and respond to these incidents, building on the underlying resilience of our energy system,” says National Energy System Operator chief Fintan Slye.
The inquiry points out that National Grid Electricity Transmission has since initiated an end-to-end review of the oil-sampling process which should have alerted the organisation to the bushing moisture problem.
National Grid Electricity Transmission says the fire was a “rare” event, and insists it has a “comprehensive asset inspection and maintenance programme in place”, with further action – including the sampling review – undertaken since the incident. It adds that it “fully” supports recommendations made by the inquiry.
Investigators have determined the electrical facility fire which forced the closure of London Heathrow was triggered by a short-circuit from moisture entering high-voltage infrastructure – a problem detected seven years earlier but left unaddressed.
The fire on 20 March, and Heathrow’s shutdown the following day, resulted in 121 flights being diverted and some 1,300 more being cancelled.
Three transformers at the North Hyde electrical facility were used to feed one of three substations at Heathrow.
Elevated moisture readings in one of the transformers’ bushings – which insulate the high-voltage conductors from other structures – were detected during maintenance in July 2018.
The reading was significant enough to indicate an “imminent fault” and require replacement of the bushing, states National Energy System Operator’s inquiry into the 20 March fire.
While the reading was recorded by National Grid Electricity Transmission, which owns the high-voltage network, the inquiry says “mitigations appropriate to its severity were not actioned”.
“The controls in place were not effective and failed to identify subsequently that action had not been taken in relation to the elevated moisture reading,” it adds.
Multiple attempts were made to schedule maintenance on the transformer but, owing to priority considerations and the need to keep systems running, none of these went ahead.
“The issue therefore went unaddressed,” the inquiry states.
Presence of moisture caused a “catastrophic” short-circuit, it states, with electrical arcing igniting oil used as a coolant.
Protections automatically disconnected the other two Heathrow-feed transformers, meaning that the airport lost one of its three substations. The airport’s management opted to reconfigure distribution from the two remaining substations, but this took several hours to carry out.
“The power outage and closure of Heathrow airport were hugely disruptive and our report seeks to improve the way parties plan for and respond to these incidents, building on the underlying resilience of our energy system,” says National Energy System Operator chief Fintan Slye.
The inquiry points out that National Grid Electricity Transmission has since initiated an end-to-end review of the oil-sampling process which should have alerted the organisation to the bushing moisture problem.
National Grid Electricity Transmission says the fire was a “rare” event, and insists it has a “comprehensive asset inspection and maintenance programme in place”, with further action – including the sampling review – undertaken since the incident. It adds that it “fully” supports recommendations made by the inquiry.
Source link
Share This:
skylinesmecher
Plan the perfect NYC Memorial Day weekend
Pack only what you need and avoid overpacking to streamline the check-in and security screening…
LA’s worst traffic areas and how to avoid them
Consider using alternative routes, such as Sepulveda Boulevard, which runs parallel to the 405 in…
London City consults on shallower glideslope to enable A320neo operations
London City airport is seeking to implement a shallower glideslope of 4.49° – compared with…
GTF shop visits continue to drive commercial maintenance revenues at MTU
MTU Aero Engines is expecting continuing strong demand for powerplant maintenance, with the persisting Pratt…
Draken boosts UK ‘Red Air’ service delivery with L-159E after completing first depot-level inspection
Adversary training specialist Draken has completed a first depot-level inspection on one of the Aero…
Rolls-Royce lifts Trent engine durability-improvement target
Rolls-Royce has hiked the durability improvement target for its Trent engine time-on-wing programme, raising the…
Strong aftermarket drives up Rolls-Royce aerospace profits despite dip in engine deliveries
While supply-chain issues dragged engine deliveries down last year, Rolls-Royce’s financial performance in civil aerospace…
Airbus plots European-developed version of autonomous H145M helicopter
Airbus Helicopters is actively pursuing a domestically-developed autonomous uncrewed version of its H145M light-twin for…
Canada’s first Pilatus PC-21 Siskin II trainer enters flight-testing in Switzerland
Pilatus has completed the first flight of a PC-21 trainer produced for the Royal Canadian…
French navy receives final upgraded ATL-2 maritime patrol aircraft
France has completed a major upgrade to its navy-operated fleet of Dassault-Breguet ATL-2 maritime patrol…
BK 160 crashed into lake during upset-recovery training but cause remains elusive
Dutch investigators have been unable to determine conclusively why a Blackshape BK 160 descended rapidly…
Ex-GTLK Europe 777-300ERs sold for engine and spares recovery
Joint liquidators of the Russian-linked leasing firm GTLK Europe have sold three Boeing 777-300ERs to…