Airbus UpNext, the airframer’s innovation arm, has completed the installation of its eXtra Performance Wing onto a Cessna Citation VII business jet that will next year serve as a flying testbed for the project.
Featuring a high aspect ratio of 17:1, the long, slender structure is equipped with folding tips and multiple automatic load-alleviation systems – based around biomimicry – designed to save weight and enhance aerodynamic efficiency.
Modification work on the Citation began in summer last year and the jet’s original wing was removed in October by project partner Tarmac Aerosave at Cazaux airbase in southwest France.
Acknowledging the unusual step, Franck Delaplace, who is in charge of the eXtra Performance Wing demonstrator, says the team “had to be careful not to damage the rest of the aircraft” during the removal process.
Prior to cutting off the wings, the business jet was suspended in a “zero-stress configuration” using a specially adapted cradle, to ensure “we did not apply any loads during that operation”, says Sebastien Blanc, technical director for the project.
Standard non-destructive testing of the fuselage then verified “that the aircraft was safe to reinstall the wing”, he adds.
Then a metallic “transition box” was installed at the wing root in late 2024, to act as a bridge between the fuselage and the new composite wing – a vital modification given that it is “a non-Airbus aircraft” says Blanc.
Installation of the wing – built at the airframer’s UK wing centre of excellence in Filton near Bristol – began in June and “more or less a couple of weeks after we put on the foldable parts”, says Delaplace.
Reassembly of the twinjet, including the refitting of its engines, was completed in July.
Ground testing of the Citation began in August, which, in addition to ground vibration, structural and aeroelastic testing of the new wing, will also include assessment of the newly installed fly-by-wire controls that replace the jet’s legacy mechanical system.
Further system testing will continue into early 2026, readying the demonstrator for its maiden sortie around mid-year; flight tests – all remotely piloted – are scheduled to run until the end of the project in December.
Blanc says the aim of the project is not only to prove the aerodynamic efficiency of the wing itself but mainly the efficacy of its “active control functions”, including morphing ailerons and pop-up spoilers linked to gust sensors fitted to the front of the aircraft.
“To make if efficient in terms of fuel consumption you need to be able to do a high-aspect-ratio wing which is light enough not to lose all your aerodynamic benefits to additional mass,” says Blanc.
The load-alleviation systems to be tested are key “enabling technologies” for a longer, thinner wing, he adds.
And while the folding wing-tips are in part incorporated to allow access to current airport gates – as seen on the Boeing 777X, for example – the “semi-aeroelastic hinge” used on the eXtra Performance Wing “could be released in flight for load alleviation purposes”, says Blanc.
Spanning some 20m (65ft), the eXtra Performance Wing fitted to the demonstrator is a scaled-down version of a narrowbody-sized structure with a span of around 50m. The folding tips account for about one-third of the length of each wing.
Outside of UpNext, the airframer is also working on wing concepts for a next-generation single-aisle through its Wing of Tomorrow programme.
Airbus UpNext, the airframer’s innovation arm, has completed the installation of its eXtra Performance Wing onto a Cessna Citation VII business jet that will next year serve as a flying testbed for the project.
Featuring a high aspect ratio of 17:1, the long, slender structure is equipped with folding tips and multiple automatic load-alleviation systems – based around biomimicry – designed to save weight and enhance aerodynamic efficiency.
Modification work on the Citation began in summer last year and the jet’s original wing was removed in October by project partner Tarmac Aerosave at Cazaux airbase in southwest France.
Acknowledging the unusual step, Franck Delaplace, who is in charge of the eXtra Performance Wing demonstrator, says the team “had to be careful not to damage the rest of the aircraft” during the removal process.
Prior to cutting off the wings, the business jet was suspended in a “zero-stress configuration” using a specially adapted cradle, to ensure “we did not apply any loads during that operation”, says Sebastien Blanc, technical director for the project.
Standard non-destructive testing of the fuselage then verified “that the aircraft was safe to reinstall the wing”, he adds.
Then a metallic “transition box” was installed at the wing root in late 2024, to act as a bridge between the fuselage and the new composite wing – a vital modification given that it is “a non-Airbus aircraft” says Blanc.
Installation of the wing – built at the airframer’s UK wing centre of excellence in Filton near Bristol – began in June and “more or less a couple of weeks after we put on the foldable parts”, says Delaplace.
Reassembly of the twinjet, including the refitting of its engines, was completed in July.
Ground testing of the Citation began in August, which, in addition to ground vibration, structural and aeroelastic testing of the new wing, will also include assessment of the newly installed fly-by-wire controls that replace the jet’s legacy mechanical system.
Further system testing will continue into early 2026, readying the demonstrator for its maiden sortie around mid-year; flight tests – all remotely piloted – are scheduled to run until the end of the project in December.
Blanc says the aim of the project is not only to prove the aerodynamic efficiency of the wing itself but mainly the efficacy of its “active control functions”, including morphing ailerons and pop-up spoilers linked to gust sensors fitted to the front of the aircraft.
“To make if efficient in terms of fuel consumption you need to be able to do a high-aspect-ratio wing which is light enough not to lose all your aerodynamic benefits to additional mass,” says Blanc.
The load-alleviation systems to be tested are key “enabling technologies” for a longer, thinner wing, he adds.
And while the folding wing-tips are in part incorporated to allow access to current airport gates – as seen on the Boeing 777X, for example – the “semi-aeroelastic hinge” used on the eXtra Performance Wing “could be released in flight for load alleviation purposes”, says Blanc.
Spanning some 20m (65ft), the eXtra Performance Wing fitted to the demonstrator is a scaled-down version of a narrowbody-sized structure with a span of around 50m. The folding tips account for about one-third of the length of each wing.
Outside of UpNext, the airframer is also working on wing concepts for a next-generation single-aisle through its Wing of Tomorrow programme.
Source link
Share This:
admin
Plan the perfect NYC Memorial Day weekend
Pack only what you need and avoid overpacking to streamline the check-in and security screening…
LA’s worst traffic areas and how to avoid them
Consider using alternative routes, such as Sepulveda Boulevard, which runs parallel to the 405 in…
Airbus installs biomimicry-inspired eXtra Performance Wing with folding tips on Citation VII flying testbed
Airbus UpNext, the airframer’s innovation arm, has completed the installation of its eXtra Performance Wing…
Certification process for Il-114-300 to finish this year: Ilyushin division chief
United Aircraft’s Ilyushin division chief is confident that the certification process for the Il-114-300 turboprop…
Swedish authority highlights sharp rise in regional satellite-navigation interference
Swedish transport regulators are to raise the issue of satellite-based navigation interference with ICAO, following…
Russian lessor GTLK to supply 50 LMS-901s to Aerokhimflot alliance
Russian state leasing firm GTLK has signed four agreements covering a total of 50 UZGA…
Raytheon UK tests Eurofighter Typhoon with Paveway IV precision-guided bomb with Italian-made warhead
Raytheon UK has completed a series of integration trials with the Eurofighter Typhoon involving its…
UK’s DSEI show to highlight spending boost as NATO nations prepare for the future
The UK’s cross-domain DSEI exhibition will be bigger and better than ever when the doors…
Royal Navy’s Malloy T-150 drone trial achieves first autonomous ship-to-ship delivery
Trial activities for the UK Royal Navy (RN) involving Malloy Aeronautics’ T-150 uncrewed air system…
L3Harris secures first retrofit order for Viper Shield electronic warfare system, for Polish F-16s
L3Harris Technologies has added Poland to its customer list for the Viper Shield electronic warfare…
Braathens to concentrate on ATR wet-lease with axing of tour-oriented Airbus fleet
Scandinavian operator Braathens has opted to simplify its fleet by phasing out its Airbus single-aisle…
Portugal’s first three Embraer A-29N Super Tucanos ready to receive NATO equipment updates
Portugal’s first three Embraer A-29N Super Tucanos touched down at OGMA’s maintenance, repair and overhaul…